Week of July 4th
Construction work has officially commenced for the installation of a new water main.
July 29, 2025
- Installed 83 feet of pipe and a 120-inch vault and valve.
- Continued trench excavation and directional boring.
- Crews will proceed toward Archer Avenue, following Damar’s alignment from 79th Street.
August 1, 2025
- Installed three (3) 20-foot sections of 8-inch water main.
- Installed one (1) 18-foot section of 8-inch water main including a tee (8″x6″) to facilitate future lateral connections.
- Valve box installation is pending and will be completed during the next phase of work.
- The water line will be reduced in diameter at the designated location to accommodate the installation of a new fire hydrant.
August 20, 2025
- Began excavation to prepare the connection of the new water main at the intersection of 87th Avenue and 79th Street.
- Coordination in place to ensure safe and efficient connection to existing infrastructure.
Prior to the start of work, proper notifications were made to the following departments:
- Building Department
- Police Department
- Village Hall
- Fire Department